Okay, so unfortunately I do not have great updates yet...2 of the 3 SRs are still "Awaiting Internal Response". These are the two requesting a different fix to closing all current projects and recreating them under the new Project Type with "contingent worker enabled".
The third SR has also not made much progress (this is the one referring to Contingent Worker timecards not importing to Projects). Here is the last correspondance we had:
1. Do you have 'Contingent Worker Enabled' selected for project type?
Yes. I have submitted timecards for existing project that were upgraded and I have submitted timecards for new projects with the contingent worker enabled selected. However, I have another SR opened to see if we can get Project Type to progate to all our projects.
2. In implementation options do you have 'Import Contingent Worker Timecards with Purchase Order Integration' selected?
This is an upgrade. In our current instance contingent workers are able to submit timecards and they upgrade fine. We do not use Purchase Orders, so this is not selected.
I'll keep you posted on any furhter progress.